MANILA, Philippines – Iniulat ng National Grid Corporation of the Philippines (NGCP) na ilang hindi naka-iskedyul na pagkawala ng kuryente ang naganap sa pitong lugar sa Luzon nitong Linggo ng gabi habang patuloy ang pananalasa ng bagyong Uwan sa kalupaan ng Luzon.

Sinabi ng NGCP na ang pagkawala ng kuryente ay naiulat sa ilang bahagi ng Ilocos Sur, La Union, Pampanga, Baguio City, Benguet, at Zambales.

Naitala ang pagkawala ng kuryente nang mag-landfall si Uwan sa Dinalungan, Aurora alas-9:10 ng gabi nitong Linggo.

Ang mga hindi naka-iskedyul na pagkaputol ng kuryente ay naitala sa mga sumusunod na lugar:

–Ilocos Sur Electric Cooperative (ISECO), Vigan Substation at 10:07 p.m., due to tripping of Bantay-Vigan 69kV line (co-maintained with ISECO)
–La Union Electric Cooperative (LUELCO), Bacnotan and Balaoan Substations at 10:27 p.m., due to tripping of Bacnotan-Bulala 69kV line
–LUELCO, Aringay, Agoo, Damortis, Alacan and Sison Substations at 10:12 p.m. due to tripping of Bauang-San Fabian 69kV line
–LUELCO, Naguilian Substation at 10:33 p.m. due to tripping of Bauang-Naguilian 69kV line
–San Fernando Electric Light and Power Company (SFELAPCO), Floridablanca Substation and Pampanga II Electric Cooperative (PELCO II), Pio and Manibaug Substation at 10:07 p.m. due to tripping of Hermosa-Floridablanca 69kV line
–Benguet Electric Cooperative (BENECO), Lamut Substation at 10:45 p.m. due to outage of La Trinidad-Lamut 69kV Line
–Zambales I Electric Cooperative (ZAMECO I), Iba, Salaza, Candelaria and Sta. Cruz Substation at 10:21 p.m. due to tripping of Botolan-Candelaria 69kV line
–BENECO, Itogon Totalizer at 10:43 p.m. due to outage of Itogon-Ampucao 23kV Line
–BENECO, North Sanitary Camp and Irisan Substations, at 10:45 p.m. due to outage of La Trinidad-Sablan 69kV Line
–LUECO, Bauang and Poro Substations at 11:16 p.m. due to tripping of Bauang-San Fernando 69kV line
–Abra Electric Cooperative (ABRECO), entire province of Abra at 11:18 p.m. due to tripping of San Esteban-Bangued 69kV, and
–ISECO at 12:21 a.m. Monday due to tripping of San Esteban-Candon 69kV line.

Ala-1:00 ng madaling araw nitong Lunes, iniulat ng NGCP ang pagpapanumbalik ng ilang transmission lines sa ilang bahagi ng Luzon. RNT/MND