Usapin sa ‘bundled’ airport privatization sa Davao, Bicol at Siargao malapit nang makompleto – CAAP

1
0

MANILA, Philippines – Malapit nang makumpleto ang negosasyon para sa pag-take over ng pribadong sektor sa tatlong regional airports sa bansa, partikular sa Davao, Bicol at Siargao, ayon sa Civil Aviation Authority of the Philippines (CAAP).

Kabilang sa proyekto ang bundled development,
operation, at maintenance ng private consortium sa Davao International Airport at Bicol International Airport sa mahigit 30-year concession period at Siargao Airport para sa 15-year concession period.

Ang P21.64 bilyong proyekto ay unsolicited proposal mula sa Philippine Regional Airports Consortium — na binubuo ng Filinvest Infra-Solutions Ventures, Inc., JG Summit Infrastructure Holding Corporation, at Asian Infrastructure and Management Corporation.

“It’s already in negotiations stage… it is about to be finished,” sinabi ni CAAP director general Raul del Rosario.

Aniya, ang bundled airports project ay nasa Public-Private Partnership (PPP) Center na.

Matapos ang negosasyon, mangyayari na ang Swiss Challenge o competitive bidding kung saan ang original proponent ay maaaring tumbasan o i-counter rival ang alok nito.

Ang scope of work sa bawat paliparan sa bundle ay ang mga sumusunod:

Davao International Airport

Phase 1 (up to 2041): Upgrade works mainly comprising passenger terminal building (PTB) expansion and renovation, upgrades to the existing cargo terminal, construction of a fire station, apron and parking lot expansion, installation of a parallel taxiway, and expansion of passenger access roads.

Phase 2 (until 2056): Capacity augmentation including further PTB expansion and renovation, construction of a new cargo terminal, additional apron and parking lot expansion, and expansion of the ground service equipment roads.

Bicol International Airport

Phase 1 (up to 2041): Renovation of the existing international area of the to enable swing operations, along with PTB expansion to accommodate additional remote gates and a new pier.

Phase 2 (until 2056): Capacity augmentation including further PTB expansion and renovation.

Siargao Airport

Phase 1 (until 2041 ): Expansion and renovation of the PTB to comply with IATA Level of Service Optimum Standards.

RNT/JGC